Line 7: Line 7:
   - The X-axis and the Z-axis leadscrews are easily accessible, applying some grease is easily done there.   - The X-axis and the Z-axis leadscrews are easily accessible, applying some grease is easily done there.
   - Before putting grease on the leadscrews, make sure they are absolutely clean. Use a soft dry cloth to clean them.   - Before putting grease on the leadscrews, make sure they are absolutely clean. Use a soft dry cloth to clean them.
-  - The Y-axis leadscrew sits under the engraving table and under a metal cover, both of which will have to be removed to get acces to them.+  - The Y-axis leadscrew sits under the engraving table and under a metal cover, both of which will have to be removed to get acces to them.\\
  
-{{:en:x200:dsc03887.jpg?600|ASCII}} \\  \\ On the above image it is clearly visible that there is no strain on the timing belt. \\  \\ Follow the 4 steps below to take off the timing belt from the spindle. \\  \\ {{:en:x200:riem_afnemen_x200.png?1200}} \\ 1. Spindle with cutter and cutter knob \\ 2. spindle with cutter and cutter knob removed \\ 3. Rotate spindle clockwise and simultaneously move the belt up on the spindle pulley \\ 4. Finally the timing belt will come off the spindle pulley. \\  \\ When putting on a new belt, first put it around the spindle motor pulley, then rotate it clockwise over the spindle pulley.+^Image  ^Description  | 
 +|{{  :en:x200:tablescrews-1.jpg?500  |{afbeelding}}|Remove the 4 screws which are indicated with a green arrow on the image on the left.| 
 +|{{  :en:x200:tablescrews-2.jpg?500  |{afbeelding}}|Remove 4 more screws which are indicated with a green arrow on the image on the left. \\ You can lift up the engraving table and put it on the side.| 
 +|{{  :en:x200:tablescrews-3.jpg?500  |{afbeelding}}|Remove the 2 screws which are indicated with a green arrow on the picture on the left.| 
 +|{{  :en:x200:tablescrews-4.jpg?500  |{afbeelding}}|Remove 2 more screws which are indicated with a green arrow on the image on the left. \\ You can lift up the leadscrew cover and put it on the side. | 
 +|{{  :en:x200:dsc03898.jpg?500  |{afbeelding}}|After having taken away the leadscrew cover you have access to the Y-axis leadscrew.\\ Clean the area which is normally covered by the engraving table and the leadscrew cover.\\ Do so using a vacuum cleaner, do not use compressed air.\\ Apply some grease to the leadscrew, just behind the leadscrew nut.\\ After having applied some grease you can re-assemble the leadscrew cover and the engraving table.| 
 +|{{  :en:x200:dsc03896.jpg?500  |{afbeelding}}|The X-axis leadscrew is easily accessible.\\ clean the leadscrew with a soft dry cloth.\\ Then apply some grease on it.| 
 +|{{  :en:x200:dsc03899.jpg?500  |{afbeelding}}|The Z-axis leadscrew is also easily accessible.\\ using the Z-axis jog keys move the spindle down and the Z leadscrew will become visible.\\ Apply some grease and move the spindle up again.|\\
  
-**Continue to [[:en:x200:greasing_the_leadscrews|greasing the leadscrews]].** \\ **Continue to [[:en:x200:table_of_contents|the table of contents]].**+ 
 + 
 + 
 + 
 +**Continue to [[:en:x200:machine_opening_the_drawer|opening the electronics compartment]].** \\ **Continue to [[:en:x200:table_of_contents|the table of contents]].**
  